Ready to spin in 100 days
A success story of the compact
spinning machine K 42
“We are very grateful to Rieter for delivering the machines on time as
well as providing the best team of technical experts for installation
and commissioning. Every member of the team did a remarkable job
in ensuring that the machines were assembled within 100 days.”
Sandeep Garg President – Operations, Nitin Spinners Ltd.
Rieter machines for bre and spinning preparation: perfectly matched technology High yarn quality thanks to the K 42 compact spinning machine
Rieter's customer Nitin Spinners Ltd. wanted to serve project team made up of experts from Sales,
a niche market as quickly as possible. Optimal Products, Operation and Service & Technology to
cooperation between the customer and Rieter has ensure smooth and rapid installation and
made this ambitious project possible. Within 100 commissioning. This gathered expertise from all
days, 72 960 compact spindles were installed. disciplines achieved perfect synergy. Co-ordination
with other suppliers, such as humidification and filter
Nitin Spinners Ltd. manufactures pure cotton yarns plants, compressed air and electricity, ran smoothly.
and fabrics for the national and international market The project was implemented in close cooperation
in Bhilwara Rajasthan, in the northwest of India. With with the customer: Regular coordination meetings
a capacity of 223 000 spindles and 3 000 rotors, Nitin were held to ensure that the right equipment was
Spinners produces 50 000 tons of yarn and 9 000 always available at the right time during the
tons of fabric per year. installation phase.
The Challenge: Fastest possible start of production The Benefits for Nitin Spinners: Ready to go within
Nitin Spinners wanted to start producing compact 100 days
yarns with the most advanced compact spinning Rieter was able to achieve all agreed values for
machines in order to offer a wider range of yarns. The productivity, yarn quality and power consumption
management's declared goal was to start as early as within the stipulated time frame. The combination of
possible in order to achieve the production targets. the best machines of their kind, coupled with a
Important for Nitin Spinners was that productivity and systematic approach, made an important contribution
quality were high and power consumption low right towards ensuring that the project could be
from the start. implemented within 100 days. The timely
commissioning enabled Nitin Spinners to meet the
The Solution: The compact spinning machine K 42 customer's order deadlines as agreed. Thanks to
After extensive consultation, the customer decided on optimum raw material utilization, the quality of the
the Rieter compact spinning machine K 42 in a yarn was improved and a high quality of the
project of 72,960 spindles. Rieter put together a Com4®compact compact yarn was achieved.